June 12, 2023

Summer Construction at HPS - Build2021

SPRING AND SUMMER 2022

Holland Language Academy Playground Improvements
-  COMPLETE

Jefferson Playground Improvements
-  COMPLETE

New Maintenance Storage Building
-  COMPLETE

Middle School Renovations – Phase 1
-  COMPLETE

Jefferson Elementary Renovations – Phase 1 (Door & Hardware Replacements)
-  COMPLETE

High School Athletic Improvements
- COMPLETE


SPRING AND SUMMER 2023

Middle School Renovations – Phase 2
-  Awarded
-  Construction – Summer 2023

MTC Card Readers, Block Heaters & Phone System
-  Design – 7/24/2022 – 10/28/2022
-  Construction – 6/1/2023 – 8/16/2023

Longfellow Building Renovation (Preparing building for Holland Heights students during 2024 Construction)
-  Design – 2/1/2023 – Summer 2023
-  Construction – 10/2023 – 4/1/2024

Holland High School Renovations
-  Design – 5/22/2022 – Summer 2023 (REVISED)
-  Construction – 6/12/2023 – 8/30/2024


SPRING AND SUMMER 2024 & Future

Holland Heights Renovations
-  Design - 1/3/2022 – 11/25/2023
-  Construction – 4/17/2024 – 8/1/2025

Administration Improvements
-  Design -  7/5/2024 – 10/24/2024
-  Construction – 6/13/2025 – 7/24/2025

West Elementary Renovations
-  Design – 1/2/2025 – 11/24/2025
-  Construction – 7/1/2026 – 8/28/2028

Jefferson Elementary Improvements – Phase 2
-  Design – 2/1/2024 – 12/4/2024
-  Construction – 4/24/2025 – 8/13/2025