GDK/OAK Construction Update-October, 2011
The most recent report from GDK/OAK is complete for the month of October. Highlights include a description of recycling efforts, a status report for the project bids, and progress on the drilling for the geothermal field. GDK/OAK . . . read more
Holland High Construction Seven Phases Through April, 2014
As outlined in the May 2010 "Build 21" construction campaign, nearly half of the $73M invested in HPS school facility renovation and technology upgrades will take place on the campus of Holland High School. Holland High's new Soccer and . . . read more
September-October 2011
The construction management firm (GDK/OAK) will be providing monthly updates to me as we continue a $34M renovation and new construction project on campus. While the linked document is prepared for the School Board, perhaps you will find . . . read more
May 2011
Design. Demolition. Construction
Note the above steps. They'll be repeated. The $34 million extreme makeover of Holland High School will continue in phases over the next three years. Even with the heavy construction scheduled for the summer months, everyone is gearing up . . . read more
"Build 21" - Progress Reports from Supt. Davis
Regular updates are found here.
Designing, renovating, and constructing efficient and effective 21st Century Learning environments is an exhausting work — but exciting as well — as we work together to shape the future of learning for every child enrolled in our . . . read more
Build 21 - Responsibilities Going Forward
October, 2010 - Chart
At the October Board of Education Meeting, Superintendent Brian Davis introduced the construction management firms who will be instrumental in our "Build 21" projects. "We stated that we would make a commitment to local economic development, . . . read more