The future HHS

Here is a pdf showing what HHS will look like when the construction is finished, and the different phases of the plan. read more

Memorials Have a Place in Holland High's New Landscape

Dr. Suess' character, The "Lorax," would not be happy about the removal of 60 trees on the Holland High campus to accommodate renovation of the school campus. And he wouldn't be alone! . . . read more

Build 21 Progress Video

Here is a 4 minute video showing progress of the Phase I construction at Holland High. read more

Build 21 Pictures - December 16, 2011

Phase One construction continues. read more

Holland High's Geo-Thermal System

October 2011 until Fall 2012

In about three years time, we will transform Holland High into a dynamic hub of 21st Century learning. We will be enhancing our technology infrastructure, increasing our energy efficiencies, and improving the safety and security of our . . . read more

Build 21 Pictures - September 29, 2011

Flag pole and scoreboard are raised on Track. read more

September-October 2011

The construction management firm (GDK/OAK) will be providing monthly updates to Brian Davis as we continue a $34M renovation and new construction project on campus. While the linked document is prepared for the School Board, perhaps you will . . . read more

Build 21 Pictures - August 25, 2011

Soccer & Tennis Complex opens to the public! Varsity (+JV) boys tennis defeat Kenowa Hills in first game played on the new courts. JV boys soccer defeat Holland Christian in first game played on new soccer field. New sport complex is . . . read more

Build 21 Pictures - August 15-19, 2011

Soccer & Tennis Complex construction nears completion: JV & Varsity boys tennis teams practice on new tennis courts for first time and parking lot space lines painted. Track surface removal continues, and construction of the . . . read more

Build 21 Pictures - August 9-12, 2011

Soccer & Tennis Complex construction continues: Painting of new tennis courts nears completion, restroom interior work continues, soccer goals & back nets installed, fencing around arch entrance continues, asphalt cement laid down in . . . read more

Build 21 Pictures - August 2, 2011

Soccer & Tennis Complex construction continues: Painting of new tennis courts continues, bench covers installed and new picnic tables arrive. Removal of dirt from the former hill continues, Track bleachers reinstalled, construction . . . read more

Build 21 Pictures - July 25-27, 2011

Tech Wing gets demolished, construction of concession buildings at baseball and softball fields begins, dirt from the former hill removed, new block wall on Track installed and Track bleachers & press box relocation begins. Soccer . . . read more

Build 21 Pictures - July 19, 2011

Hill along Track & Field removed and track surface construction continues. Soccer & Tennis Complex construction continues: new trees planted in new parking lot and fencing goes up around arch entrance. read more

Build 21 Pictures - July 12, 2011

Track & Field and former Tennis Courts surface removed. Soccer & Tennis Complex construction continues: Parking lot construction continues, water/sprinkler system installed, fencing goes up around soccer field and tennis courts . . . read more

Build 21 Pictures - July 11, 2011

Soccer and Tennis coaches tour the construction progress of the new Soccer & Tennis complex. read more

Build 21 Pictures - July 5-7, 2011

Pre-Tech Wing demolition work begins (includes last interior look of the Tech Wing). Soccer & Tennis Complex construction continues: new parking lot construction continues, tennis court construction continues, concession stand . . . read more

Build 21 Pictures - June 28, 2011

Soccer & Tennis Complex construction continues: Walkway construction continues, tennis court construction continues, restroom interior work begins, soccer field construction continues and new parking lot construction begins. read more

Build 21 Pictures - June 21-24, 2011

Soccer & Tennis Complex construction continues: Sewer/drainage system construction completed, artificial turf on soccer field completed, fence poles go up around new entrance, tennis court gazebo receives a roof, sidewalk along Van Raalte . . . read more

Build 21 Progress Video

Here is a 5 minute video showing progress at Holland Heights, Holland New Tech, and Holland High. It may take a few minutes to load. read more

Build 21 Pictures - June 14-15, 2011

Soccer & Tennis Complex construction continues: Artificial turf is rolled out onto soccer field, walkway construction continues and new sewer/drainage system construction begins. read more

Build 21 Pictures - June 14, 2011

Build 21 Steering Committee tours Holland's High's Soccer & Tennis Complex. read more

Build 21 Pictures - June 13, 2011

Soccer & Tennis Complex construction continues: Remainder of former student parking lot is removed, concession stand/restroom building receives paint, walkway construction begins, tennis court gazebo constructed, ballast rock on soccer . . . read more

Summer 2011 Construction Info

Here is a Power Point Presentation from Principal Klomparens about summer construction and fall parking for Holland High School.   read more

Build 21 Pictures - June 1, 2011

Soccer & Tennis Complex construction continues: Concession stand/restroom building receives a roof, fence poles and water drainage system surrounding tennis courts installed, new trees planted along soccer field, ballast rock poured onto . . . read more

Build 21 Pictures - May 17, 2011

Soccer & Tennis Complex construction continues: Concession stand/restroom building construction begins to take shape and construction of new tennis courts begins. read more

Build 21 Pictures - April 12, 2011

Construction of Holland High's new Soccer & Tennis Complex begins. read more

Build 21 Pictures - March 15, 2011

Pre-Construction begins with the removal of fencing and poles from the soccer field complex. read more